Subaru Legacy/Outback

1999-2003 of release

Repair and car operation



Subaru Legasi, Autbek
+ Cars Subaru Legacy, Outback
+ The operation manual
+ Routine maintenance
+ The engine
+ Systems of cooling, heating
+ The power supply system and release
+ Engine electric equipment
- Manual box and differential
   Specifications
   The mechanism of blocking of inclusion of a reverse gear - the device and a functioning principle
   Interaxal differential - the device and a functioning principle
   Removal and installation трансмиссионной assemblages
   Check of a condition and replacement of elements of support of a suspension bracket трансмиссионной assemblages
   Check of a condition and epiploon replacement
   Removal, installation and check of a condition of gauges-switches
   Removal, installation and check of a condition of the gauge of speed (VSS)
   Preparation for performance of major repairs РКПП
   Removal, service and installation of a distributing box and transmission lengthening
   Removal, service and installation of a leading gear wheel of the distributing mechanism
   Removal, service and installation of a conducted gear wheel of the distributing mechanism
   Removal, service and installation of interaxal differential
   Removal, service, installation and adjustment of assemblage of the mechanism of blocking of inclusion of a reverse gear
   Removal, installation and condition check картера трансмиссионной assemblages
   Removal, service, installation and adjustment of primary shaft РКПП
   Removal, service and installation of entrance shaft РКПП (models with an additional two-level reducer)
   Removal, service and installation of assemblage of a shaft of a leading gear wheel of the main transfer of a drive of forward wheels
   Removal, service, installation and adjustment of forward differential
   Removal, installation and check of a condition of a gear wheel of a drive of a speedometer
   Removal, installation and adjustment of an intermediate gear wheel of a reverse gear
   Removal, installation, check and adjustment of assemblage of gear wheels of a two-level reducer
   Removal, check of a condition and installation of plugs and gear change rods
   Removal, service and installation of the lever of gear change РКПП
   Removal, service and installation of the lever of switching of modes «Hi/Lo» an additional two-level reducer
   Removal, service and installation тросовой draughts of a drive of switching of modes of a two-level reducer
+ Automatic transmission
+ Coupling
+ Brake system
+ Suspension bracket and steering
+ Body
+ Onboard electric equipment

Removal, service and installation of interaxal differential

REMOVAL

 PERFORMANCE ORDER

1. Remove assemblage РКПП (see Has undressed Removal and installation трансмиссионной assemblages).
2. Remove assemblage of a distributing box with transmission lengthening (see Has undressed Removal, service and installation of a distributing box and transmission lengthening).
3. Remove lengthening of transmission from a distributing box (see Has undressed Removal, service and installation of a distributing box and transmission lengthening).
4. Take a conducted gear wheel of the distributing mechanism (see Has undressed Removal, service and installation of a conducted gear wheel of the distributing mechanism)
5. Take assemblage of interaxal differential.

CHECK

 PERFORMANCE ORDER

1. Grease bearings and manually estimate smoothness and noiselessness of their rotation, check up bearings on presence of signs of excessive deterioration, traces of development of corrosion. Defective components replace.
2. Estimate degree of deterioration of components of differential, defective assemblage replace.

Bearing replacement

 PERFORMANCE ORDER

 The interaxal differential is not subject to dismantling and in case of damage of internal components is replaced in gathering.


1. By means of special adaptation ST 498077300 remove the ball bearing of interaxal differential.

 The removed bearing is not subject to a reuse and should is replaced without fail!

2. Landing of the new bearing is made by means of approaching оправки.

 The put landing effort should not exceed 10 кН (1 ton)!

INSTALLATION

 PERFORMANCE ORDER

Installation is made in an order, the return to an order of dismantle of components.


On the main page